What six grazing horses tell us about England's housing crisis
0 / 78
English
中文
Watch: What happened to the 7,400 homes promised across these three developments?
(暂无翻译)
About a five-minute walk from the train station in Middlesbrough, six horses are grazing lazily on a derelict patch of land.
(暂无翻译)
Tethered and friendly, the animals do not attract much attention from residents, despite being so close to the town centre.
(暂无翻译)
But their presence on the land, by the banks of the River Tees, is a symbol of the UK's decades-long failure to build enough houses.
(暂无翻译)
In 2004, the local council announced plans to build 2,400 homes on the grass the horses are eating.
(暂无翻译)
But 22 years later, just 216 homes have been built. The money initially outlined for the project has never been found.
(暂无翻译) (暂无翻译)
The UK is in a housing crisis with demand for homes continuing to outstrip supply.
(暂无翻译)
To understand why successive governments have failed to build enough houses, BBC News went to this Middlesbrough scheme, and planned developments in York and the Isle of Sheppey, in Kent.
(暂无翻译)
Each has its own story, with finances, infrastructure planning and developers' appetites all playing a major role - issues mirrored at other sites across the country.
(暂无翻译)
Combined, the projects we visited promised to build 7,400 homes. To date, just 326 have been constructed.
(暂无翻译) (暂无翻译)
Shortfalls like this affect national goals significantly, says Anthony Breach, director of policy and research at the Centre for Cities think tank.
(暂无翻译)
The UK's reliance on "large, complex schemes" to deliver new housing means that "when our larger sites get a bit stuck, that has a disproportionate impact on national housebuilding", he says.
(暂无翻译)
These large-scale projects, increasingly favoured by private developers and often driven by local councils, are key to the Labour government's target of building 1.5 million homes in England by the next election.
(暂无翻译)
The 2004 plans for Middlehaven in Middlesbrough, a long-disused industrial site, included not just thousands of homes but also a theatre, restaurants and hotels.
(暂无翻译)
It was billed as a £500m development, but it had one fundamental flaw: the money never existed.
(暂无翻译)
Instead, this figure was simply an estimate of overall cost, Middlesbrough Council told us.
(暂无翻译)
Almost a decade later, in 2013, the development was proposed again. This time, the council bought 185 homes that already existed, so they could be demolished to make space.
(暂无翻译) (暂无翻译)
Yet only 216 homes have been built to replace them, a net gain of 31.
(暂无翻译)
Some buildings, like these offices, have been constructed on the Middlesbrough site The council says delivery of the masterplan was curtailed by the 2008 financial crash, "leading to the departure of the council's development partner".
(暂无翻译)
A college campus, business space and housing have been delivered, it says, and a new school is being built.
(暂无翻译)
The price that new homes will sell for is a key factor in large developments progressing, says Breach, as housebuilding firms look for returns on their investments.
(暂无翻译)
In places where house prices are lower, he says, public sector funds may be needed to "bridge the gap between the cost of building [works] and the price at which the houses can be sold for".
(暂无翻译)
In September, Middlesbrough Council announced plans for 462 new homes on the site - the beginning, it hopes, of a development of 3,400 homes in all.
(暂无翻译)
This time, however, the council is far more cautious, acknowledging the money might not be there to achieve everything it would like.
(暂无翻译)
In York, a plan for 3,000 homes was announced in 2001, but a quarter of a century later, not a single house has been built.
(暂无翻译)
Alongside the homes, close to the historic centre of the city, were to be business and hospitality opportunities - just like in Middlesbrough.
(暂无翻译)
The site in York that is yet to be developed Planning consultant Nora Galley was hired by the local council to develop the York Central masterplan.
(暂无翻译)
Her designs, she tells the BBC, combined a realistic vision with a plan to deliver it.
(暂无翻译)
"It wasn't just a beautiful place that looked great in architect's drawings," she says.
(暂无翻译)
But by the time the 2008 crash hit, work had not begun.
(暂无翻译)
In September this year, the project's first phase was finally given the green light, with some 2,500 homes planned to be built by 2040.
(暂无翻译)
"There is no fabric in this country to manage the delivery of strategic projects," says Nora Galley Galley is disappointed that construction has taken so long to get under way, and that fewer homes will be built than originally planned.
(暂无翻译)
"There is no fabric in this country to manage the delivery of strategic projects," she tells us - highlighting what she sees as supply chain issues and a lack of construction training.
(暂无翻译)
In June, trade body the Construction Industry Training Board, external backed Galley's point - citing a need for 206,000 new construction workers across the UK between now and 2030.
(暂无翻译)
York Central is now set to cost £2bn to complete, far more than the hundreds of millions of pounds local papers reported when plans were first set out.
(暂无翻译)
Delays to the project have cost York greatly, says Galley.
(暂无翻译)
The city has missed out on "wealth, opportunities, a better-performing economy".
(暂无翻译)
The first houses should be built within two years, says Claire Douglas, leader of City of York Council Residents we spoke to were largely in favour of York Central, seeing its potential.
(暂无翻译)
But all seemed puzzled by the amount of time it had taken. Cycle lanes, pristine paths and bus stops surround the site, yet nobody was around to use them.
(暂无翻译) (暂无翻译)
"I had colour in my hair when they first announced it," quips one middle-aged woman who lives in the neighbouring estate.
(暂无翻译)
The main problem has been the site's positioning, surrounded by railway lines, says Labour leader of City of York Council, Claire Douglas. The project stalled because, for a time, there was no money from government to pay for an access road allowing construction materials on to the site, she says.
(暂无翻译) (暂无翻译)
But now the access road is nearing completion and the first houses should be built within two years, she says. Nearly 200 miles (322km) south, on the Isle of Sheppey in Kent, a planned development of up to 2,000 new homes was meant to help regenerate a deprived part of the island.
(暂无翻译) (暂无翻译)
It is now 23 years since the plan was initially conceived, and 17 years since it was backed by local councils.
(暂无翻译)
But only 110 houses have been built.
(暂无翻译)
The project was hailed in a 2009 press release as a "£400m regeneration" of the area, but Swale Borough Council has told the BBC that, as in Middlesbrough, the money never actually existed.
(暂无翻译)
The figure, it said, was an estimation "of the likely investment required to deliver the scheme at that time", and there was no housing developer lined up.
(暂无翻译)
A development of 2,000 homes was planned to be built at this site on the Isle of Sheppey Some 3,000 jobs were also expected to be created, but only some have materialised. A retail park housing a Morrisons, Burger King and Sports Direct among other outlets has been completed, but plans for a marina have been scrapped.
(暂无翻译) (暂无翻译)
Where the hundreds of homes should stand is an empty field surrounded by metal railings.
(暂无翻译)
Locals say the grass is occasionally mowed.
(暂无翻译)
Meanwhile, the council has 1,800 households waiting for social housing.
(暂无翻译)
"We do need a few more houses [here], but we also need more doctors and things like that as well," says Marie Miller, lifelong resident of the neighbouring village of Rushenden.
(暂无翻译)
Along with new homes, local amenities need to be provided, says resident Marie Miller The planned "state of the art" healthcare centre on the same site remains unbuilt.
(暂无翻译)
Nothing has happened on the site in a long time, Miller says. The original 2,000-homes plan was scaled back in 2015 to 1,180, but even this reduced figure is unlikely to be achieved.
(暂无翻译) (暂无翻译)
According to council documents, the project is back at the planning stage.
(暂无翻译)
Homes England, the government's housing and regeneration agency, is now approaching housebuilders for their "early observations" about developing the site.
(暂无翻译)
After the economic downturn of 2008, the planned level of development "proved to be an optimistic forecast", the local council said, adding it was "working closely with Homes England to agree an updated timescale".
(暂无翻译)
These three schemes we have visited are not the only projects to have failed to deliver new housing over long time periods.
(暂无翻译)
In London, where housebuilding has fallen substantially in recent years, not one of the 3,500 homes planned for Convoy's Wharf in Deptford has been built - despite outline planning permission being given in 2005.
(暂无翻译)
Planning problems and objections from locals have contributed to the delays. On the north side of the Thames, a 2008 plan to build 10,800 units at Barking Riverside was stalled for years because of poor transport links.
(暂无翻译) (暂无翻译)
However, since the creation of a new rail line, 3,000 homes now have been built and plans have been approved to almost double the housing development to 20,000 homes.
(暂无翻译)
The glacial speed at which things get done, particularly at the sites we visited in Middlesbrough, York and Kent, offer key insights as to why the UK has not built as many homes as it needs.
(暂无翻译)
Local politicians may deny planning applications even if developers follow all the rules, says Anthony Breach Part of the housebuilding challenge, says Anthony Breach from Centre for Cities, is that the UK's planning system is "pretty unusual internationally".
(暂无翻译)
Even if a developer follows all the rules "you can still be denied planning permission by local politicians", he says - meaning developments take much longer, and risk being upended if a new party is elected locally. To overcome planning delays, mayoral development corporations (MDCs) are increasingly being established by England's regional mayors.
(暂无翻译) (暂无翻译)
These bodies can take planning duties away from a local authority and make compulsory land purchases, enabling large-scale projects to move more quickly. Breach sees this as a positive step, describing MDCs as a shortcut through the planning system that should see housebuilding increase.
(暂无翻译) (暂无翻译)
A spokesperson for the Ministry of Housing told the BBC it was "working with Homes England to get stalled schemes moving, with housing starts up 20% on this time last year".
(暂无翻译)
They added: "We've unblocked and accelerated more than 130,000 homes and, through our planning overhaul and £40bn Social and Affordable Homes Programme, we are unlocking development and building the homes our country needs."
(暂无翻译)
The schemes in Middlesbrough, York and Kent may eventually come good - but decades later than promised, their failures all contributing to the UK's chronic lack of housing. 'Just push us into the sea': The frustration of an area failed by politics Why one small town with very little immigration turned to Reform UK What an empty car park tells us about the UK's debt problem The town whose council wants migrants to move in